CompTIA PK0-005 Question Answer
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?