A project manager and team are reviewing a task that is supposed to take 9...

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

13 days and $3,600

CompTIA PK0-005 Summary

  • Vendor: CompTIA
  • Product: PK0-005
  • Update on: Aug 13, 2025
  • Questions: 362
Price: $52.5  $149.99
Buy Now PK0-005 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method