A project manager notices a resource is overloaded and not completing tasks on time.

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

CompTIA PK0-005 Summary

  • Vendor: CompTIA
  • Product: PK0-005
  • Update on: Sep 18, 2025
  • Questions: 386
Price: $52.5  $149.99
Buy Now PK0-005 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method