During the project initiation phase, a project team has been identified.

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule