Following a successful release, a project manager sent a survey to all stakeholders to gain...

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes