Participant attendance has been poor at the last few weekly meetings.

Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?

A.

Project communication plan

B.

Project management plan

C.

Project business case

D.

Project schedule

CompTIA PK0-005 Summary

  • Vendor: CompTIA
  • Product: PK0-005
  • Update on: Sep 16, 2025
  • Questions: 386
Price: $52.5  $149.99
Buy Now PK0-005 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method