Black Friday Lightning Deal: 75% Off Exam Bundles! Use coupon code below for instant savings! - Ends in 0d 00h 00m 00s - Coupon code: vce75

While developing a project charter, a PM discovers that some of the legal requirements have...

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

CompTIA PK0-005 Summary

  • Vendor: CompTIA
  • Product: PK0-005
  • Update on: Nov 24, 2026
  • Questions: 460
Price: $52.5  $149.99
Buy Now PK0-005 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method