A PMO professional overseeing multiple projects notices that project managers have varying levels of adherence...

A PMO professional overseeing multiple projects notices that project managers have varying levels of adherence to the project governance processes.

What should the PMO professional do first to ensure consistent governance across projects?

A.

Schedule individual meetings with project managers to understand their challenges with governance processes and provide support.

B.

Develop a comprehensive governance training program and mandate all project managers to complete it within a specified timeframe.

C.

Escalate governance oversight responsibilities to project sponsors to ensure project managers adhere to processes.

D.

Implement stricter enforcement of the governance processes by imposing fines and other penalties for noncompliance.

PMI PMI-PMOCP Summary

  • Vendor: PMI
  • Product: PMI-PMOCP
  • Update on: Dec 29, 2025
  • Questions: 120
Price: $52.5  $149.99
Buy Now PMI-PMOCP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method