A feature has been added to the iteration backlog that has been prioritized by the...

A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?

A.

Perform a risk analysis and then meet with the project sponsor to discuss it.

B.

Meet with the project sponsor to discuss the feature with the product owner.

C.

Push back on the feature because it is not an immediate priority.

D.

Give all the work packages parallel priority and continue activities.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method