Key decision makers are meeting to define the objectives of a new database migration project.

Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.

How should the project manager impartially prioritize the requirements to be integrated?

A.

Retain only requirements that result in profitable revenue growth.

B.

Ensure the CEO selects the requirements from all department leaders.

C.

Give each department a fixed budget that will cover ten requirements.

D.

Rank the requirements with the highest benefit-cost ratio as more important.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method