A project is nearing finalization and just released the final product to the customer.

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

A.

Schedule a lessons learned meeting with the project team and close out the project.

B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.

C.

Prepare a transition plan to hand over the operations and other closing documentation.

D.

Document the project manager's departure and the missing documents in the risk log.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method