A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted
that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?