A project manager agreed to a team member's request to have an alternative working schedule...

A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each

day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the

company's core working hours begin at 9:00 a.m.

What should the project manager have done to prevent this situation?

A.

Broken down the situation to identify the root cause

B.

Determined communication methods and channels

C.

Analyzed the boundaries of the negotiations for agreement

D.

Managed and rectified the ground rule violations

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method