Summer Special Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: vce65

A project manager has been given a critical, 5-day window and is allocated a maximum...

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.

B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.

C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.

D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method