PMI PMP Question Answer
A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.
What should the project manager do?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Oct 19, 2025
- Questions: 594