An agile project is in its ninth of 10 iterations.

An agile project is in its ninth of 10 iterations. The team is delivering the work as expected. In the planning session, the team identifies a dependency with another project in the organization.

What should the scrum master do in order to accomplish the iteration goal?

A.

Ask the product owner to collaborate with the other team about the dependency.

B.

Recommend that the product owner change the priority of the dependency.

C.

Initiate collaboration with the other project team working on the dependency.

D.

Ask a team member to interact with the other team to complete the dependency.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method