The velocity of the team is decreasing at every iteration.

The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.

Which three actions should the project manager take? (Choose three)

A.

Conduct a root cause analysis (RCA) and identify a solution.

B.

Elaborate on the plan to implement a solution and execute it.

C.

Increase the working time to recover the lost time.

D.

Negotiate with the teams involved to manage team dependencies.

E.

Evaluate the effectiveness of the proposed solution.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method