PRINCE2 PRINCE2-7-Practitioner Question Answer
Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.
During which ‘managing a stage boundary’ activity should this recommendation be developed?