PRINCE2 PRINCE2-7-Practitioner Question Answer
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?