While preparing the project plan during initiation, the project manager proposes that stage 2 should...

While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

A.

Yes, because a stage boundary may be aligned with an important external decision point, such as a funding approval

B.

Yes, because every stage may end immediately after one specialist product has been completed and funding has been approved

C.

No, because stage length must be determined solely by the level of risk

D.

No, because stage length must be determined by the technical complexity of the work

PRINCE2 PRINCE2-7-Practitioner Summary

  • Vendor: PRINCE2
  • Product: PRINCE2-7-Practitioner
  • Update on: Oct 2, 2026
  • Questions: 56
Price: $52.5  $149.99
Buy Now PRINCE2-7-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method