While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting...

While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.

Is this an appropriate application of the organization practice, and why?

A.

Yes, because the Mayor may delegate responsibility for appointing the project executive to any senior stakeholder involved in the project

B.

Yes, because the Portfolio Director, as the business layer representative, takes responsibility for appointing the project executive

C.

No, because it is the Mayor, as the senior elected authority, who should personally select and appoint the project executive for a project of this civic significance

D.

No, because the responsibility for commissioning and initiating projects within the LOB portfolio rests with the Head of Portfolio Office, not the Portfolio Director

PRINCE2 PRINCE2-7-Practitioner Summary

  • Vendor: PRINCE2
  • Product: PRINCE2-7-Practitioner
  • Update on: Oct 2, 2026
  • Questions: 56
Price: $52.5  $149.99
Buy Now PRINCE2-7-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method