The executive has asked the project manager to plan for the 'e-learning course' to be...

The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case.

Why is the executive's decision to deliver the benefits early appropriate for managing the business case?

A.

Because organizations with mature project management often include the early justification for the project in the business case.

B.

Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.

C.

Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.

D.

Because the business case should be updated after every increment of the 'e-learning course'.

PRINCE2 Prince2-Practitioner Summary

  • Vendor: PRINCE2
  • Product: Prince2-Practitioner
  • Update on: Feb 7, 2026
  • Questions: 263
Price: $52.5  $149.99
Buy Now Prince2-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method