The project is in stage 3.

The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.

Is this an appropriate action, and why?

A.

Yes, because an exception report should be used to request guidance on how this situation should be handled.

B.

Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.

C.

No, because the project manager should check the operations and maintenance interfaces in the work package first.

D.

No, because the team plan should be discussed with the supplier to check whether work will be completed on time.

PRINCE2 Prince2-Practitioner Summary

  • Vendor: PRINCE2
  • Product: Prince2-Practitioner
  • Update on: Feb 7, 2026
  • Questions: 263
Price: $52.5  $149.99
Buy Now Prince2-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method