Scrum PSM-II Question Answer
At the ninth Sprint Retrospective, the Product Owner is very disappointed and angry. She has determined that the technical debt has increased, and the product is not meeting her expectations. The product will need a few more Sprints to meet the scalability requirements.
Which of the following could be true? Select the best response.
(choose the best answer)