Five new Scrum Teams have been created to build one product.

Five new Scrum Teams have been created to build one product. A few of the Developers ask the Scrum Master who will coordinate the work between the different Scrum Teams. What should the Scrum Master do?

(choose the best answer)

A.

Visit the five Scrum Teams each day to facilitate alignment and synchronization of their Sprint Backlogs.

B.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

C.

Teach the Product Owner to work with the lead developers on ordering Product

Backlog in a way to avoid too much technical and development overlap during a

Sprint.

D.

Teach them that it is their responsibility to form Scrum Teams with the skills and knowledge to create an Increment by the end of every Sprint.

E.

Advise the teams to reduce interdependence by working in separate branches and organizing a specific Sprint every four development Sprints to manage integration.

Scrum PSM-II Summary

  • Vendor: Scrum
  • Product: PSM-II
  • Update on: Jul 28, 2025
  • Questions: 74
Price: $52.5  $149.99
Buy Now PSM-II PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method