Jenny is the project manager for her organization.

Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task?

Each correct answer represents a complete solution. Choose all that apply.

A.

Scenario building

B.

Technology forecasting

C.

Autoregressive moving average

D.

Forecast by analogy

GIAC GCPM Summary

  • Vendor: GIAC
  • Product: GCPM
  • Update on: Jul 25, 2025
  • Questions: 397
Price: $52.5  $149.99
Buy Now GCPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method