You are a new Project Manager that has been entrusted with a software development project. You have started building the list of activities and sequencing them for your project schedule model. As part of the activities, you have identified that your project team will need to start resolving the defects that come out of the User Testing, 5 days after the testing starts. Which of the following would be the correct way to represent this logical relationship between the activities?